Street Reconstruction Project 19-3 – 3.3 miles of residential streets
The Contractor for this project is Douglas-Kerr Underground, Inc. The Contractor's main contact is Ryan Kerr, who can be reached at 320-679-8937 (office) or 320-515-0046 (cell). Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work during the week of October 7 includes placement of the final lift of asphalt pavement in the Phase 1B area (Bridgewater neighborhood consisting of Alder Street, Butternut Street, Cottonwood Street, 116th Avenue, 116th Lane, and 117th Avenue).
Concrete sidewalk and curb replacements should be completed on the east side of Springbrook Drive and Holly Street. Asphalt paving will take place on the northbound lanes of Springbrook Drive and Holly Street by the end of the week.
Grading and preparation for sidewalk replacements will continue on Mississippi Boulevard from Hanson Boulevard to Ibis Street.
Boulevard restorations will continue on Flora Street north of 109th Lane, adjacent to the Coon Rapids Ice Center.
New concrete sidewalk and curb replacements are planned to be completed on the East River Road Service Road between Larch Street and 84th Lane.