Construction Updates

To sign up for email notifications of these weekly updates, click Notify Me and select “Construction Updates.”

If you have any questions throughout construction season, please email Engineering@coonrapidsmn.gov or call 763-767-6479. 

Street Reconstruction Project 19-1 – 4 miles of residential streets

The Contractor for this project is North Valley, Inc. The Contractor's main contact is Herb Thielbar, who can be reached at 763-274-2580 (office) or 612-716-4214 (cell). Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).

Work planned for the week of September 30 includes sidewalk construction along the north side of 131st Avenue between the Coon Creek bridge and Coon Creek Boulevard. Remaining concrete work will be completed throughout the entire phase 3 area (north and south of 131st Avenue).

Driveway paving, irrigation repairs, and topsoil placement is expected on properties within the phase 3 area located north of 131st Avenue. 

Street Reconstruction Project 19-2 – 2.3 miles of MSA streets (Foley Boulevard from 115th Avenue to 124th Avenue, Wedgewood Drive from Main Street to Round Lake Boulevard, Olive Street from 121st Avenue to Main Street) 

The Contractor for this project is Park Construction. The Contractor's main contact is Dan Bodza, who can be reached at 612-248-7760 (cell). Rene Garcia (612-360-4707) with Park Construction is the Contractor point of contact for watermain pipe replacements. Jon Halter with Hakanson Anderson is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jon can be reached at 612-282-0725 (cell).

Work planned for the week of September 30 includes boulevard restorations on Wedgewood Drive, and potentially paving the final lift of asphalt pavement by the end of next week.

Installation of crosswalks and lane striping is planned for Olive Street on Wednesday, October 2.

Paving of the new asphalt trail on the east side of Foley Boulevard is planned to take place next week. Work will continue all week on the Sand Creek culvert replacements. Foley Boulevard will remain closed to traffic for the foreseeable future as this culvert replacement work continues.  

To accommodate the Sand Creek culvert replacements, Foley Boulevard is closed at the Sand Creek crossing south of 118th Avenue. A posted detour is currently in place from Northdale Boulevard to 121st Avenue via University Avenue (local access will be maintained).

Street Reconstruction Project 19-3 – 3.3 miles of residential streets 

The Contractor for this project is Douglas-Kerr Underground, Inc. The Contractor's main contact is Ryan Kerr, who can be reached at 320-679-8937 (office) or 320-515-0046 (cell). Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).

Work during the week of September 30 includes mailbox restorations within the watermain replacement areas of the Phase 1B area (Bridgewater neighborhood consisting of Alder Street, Butternut Street, Cottonwood Street, 116th Avenue, 116th Lane, and 117th Avenue).

Concrete sidewalk and curb replacements are planned for the east side of Springbrook Drive and Holly Street. Asphalt paving is tentatively planned for the northbound lanes of Springbrook Drive by the end of the week.

Grading and preparation for sidewalk replacements is planned for Mississippi Boulevard (Hanson Boulevard to Ibis Street).

Boulevard restorations will continue on Flora Street north of 109th Lane (adjacent to the Coon Rapids Ice Center).

New concrete sidewalk and curb replacements are planned for the East River Road Service Road between Larch Street and 84th Lane.

Port Riverwalk Development Project 19-12 – Grading, Erosion Control, and Turf Establishment 

The Contractor for this project is North Pine Aggregate. The Contractor's main contact is Jake Jensen, who can be reached at 651-888-7907 (office) or 612-770-6682 (cell). Ron Sample is the City’s project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-767-6427 (office) or 763-257-3874 (cell).

Work during the week of September 30 includes continued removals and mass grading for the new Port Riverwalk development. Local traffic will continue to be able to use Zilla Street/East River Boulevard and Egret Boulevard to access Coon Rapids Boulevard. 

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-324-3114.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly  

Proposed 2020 Projects  

Planning for 2020 street reconstruction projects is underway! At the September 3, 2019 City Council meeting, staff recommended two projects: 20-1 consists of approximately 2.6 miles of residential streets, and 20-2 includes approximately 2.1 miles of Municipal State Aid (MSA) streets and 0.2 miles of local streets. For more information and to view proposed project locations, visit: www.coonrapidsmn.gov/2020Projects

Watch our Videos!   

Watch the City’s street reconstruction videos to learn more about the process! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

View them here: www.coonrapidsmn.gov/843/Street-Reconstruction