Construction Updates

To sign up for email notifications of these weekly updates, click Notify Me and select “Construction Updates.”

Letters with project and schedule information were mailed to property owners within street reconstruction areas 19-1, 19-2, and 19-3. If you would like a copy, please email Engineering@coonrapidsmn.gov or call 763-767-6479. 

Street Reconstruction Project 19-1 – 4 miles of residential streets

The Contractor for this project is North Valley, Inc. The Contractor's main contact is Herb Thielbar, who can be reached at 763-274-2580 (office) or 612-716-4214 (cell). Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).

Work during the week of July 15 will include asphalt paving and boulevard restoration for streets within Area 2 (Partridge Street, Raven Street, 123rd Lane, and 124th Avenue). Concrete saw-cutting is scheduled for streets within the last phase of the project (streets north and south of and including 131st Avenue). Concrete removals are planned for streets south of 131st Avenue. 

Street Reconstruction Project 19-2 – 2.3 miles of MSA streets (Foley Boulevard from 115th Avenue to 124th Avenue, Wedgewood Drive from Main Street to Round Lake Boulevard, Olive Street from 121st Avenue to Main Street) 

The Contractor for this project is Park Construction. The Contractor's main contact is Dan Bodza, who can be reached at 612-248-7760 (cell). Rene Garcia (612-360-4707) with Park Construction is the Contractor point of contact for watermain pipe replacements. For the week of July 15, Andy Evans with Hakanson Anderson will be the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

Work during the week of July 15 includes continued construction of the new watermain system on Olive Street. Grading, curb installations, and boulevard restorations will continue on the west side of Foley Boulevard. 

Street Reconstruction Project 19-3 – 3.3 miles of residential streets 

The Contractor for this project is Douglas-Kerr Underground, Inc. The Contractor's main contact is Ryan Kerr, who can be reached at 320-679-8937 (office) or 320-515-0046 (cell). Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).

Work during the week of July 15 includes grading and asphalt pavement installation on streets in the Phase 1A area (Flintwood Street, Goldenrod Street, 114th Avenue, 116th Avenue, Evergreen Street, Evergreen Circle, and 117th Avenue). Irrigation repairs in the Phase 1A area will also take place. Permanent watermain construction will continue next week in the Phase 1B area (Bridgewater neighborhood consisting of Alder Street, Butternut Street, Cottonwood Street, 116th Avenue, 116th Lane, and 117th Avenue). 

Trail Reconstruction Project 19-9 – Erlandson Park Pedestrian Bridge & Dahlia Park Culvert Installation 

The Contractor for this project is Blackstone Contractors. The Contractor's main contact is Brooks Duesterhoeft, who can be reached at 763-291-7728 (office) or 763-267-9411 (cell). Hafedh Hlel is the City’s project engineer/inspector, and can be contacted any time to respond to specific questions or concerns. Hafedh can be reached at 763-767-6412 (office) or 763-339-6128 (cell).

This project is planned to begin the week of July 22nd. 

Trail Reconstruction Project 19-11 – Wedgewood Trail, Nelson Park Trails, and Trackside Park Trails 

The Contractor for this project is Northwest Asphalt. The Contractor's main contact is John Hamers, who can be reached at 952-445-1003 (office) or 952-292-8471 (cell). Hafedh Hlel is the City’s project engineer/inspector, and can be contacted any time to respond to specific questions or concerns. Hafedh can be reached at 763-767-6412 (office) or 763-339-6128 (cell).

Construction during the week of July 15 includes work on final turf and concrete restorations on the Wedgewood Trail system, as well as Nelson and Trackside Parks. 

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-324-3114.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly  

Watch our Videos!   

Watch the City’s street reconstruction videos to learn more about the process! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

View them here: www.coonrapidsmn.gov/843/Street-Reconstruction