Letters with project and schedule information were mailed to property owners within street reconstruction areas 19-1, 19-2, and 19-3. If you would like a copy, please email Engineering@coonrapidsmn.gov or call 763-767-6479. 

Street Reconstruction Project 19-1 – 4 miles of residential streets

The Contractor for this project is North Valley, Inc. The Contractor's main contact is Herb Thielbar, who can be reached at 763-274-2580 (office) or 612-716-4214 (cell). Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).

Work during the week of July 8 will include asphalt pavement reclamation for streets within Area 2 (Partridge Street, Raven Street, 123rd Lane, and 124th Avenue). The Contractor will remove excess gravel and prepare the streets for asphalt base course paving. Periodic tree removals are also planned for the streets within phase 3 (streets north and south of and including 131st Avenue). 

Street Reconstruction Project 19-2 – 2.3 miles of MSA streets (Foley Boulevard from 115th Avenue to 124th Avenue, Wedgewood Drive from Main Street to Round Lake Boulevard, Olive Street from 121st Avenue to Main Street) 

The Contractor for this project is Park Construction. The Contractor's main contact is Dan Bodza, who can be reached at 612-248-7760 (cell). Rene Garcia (612-360-4707) with Park Construction is the Contractor point of contact for watermain pipe replacements. Jon Halter with Hakanson Anderson is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jon can be reached at 612-282-0725 (cell).

Work during the week of July 8 will include construction of the new watermain system on Olive Street (starting mid to late in the week). Boulevard restorations (topsoil placement, irrigation repairs, and sod installation) will begin on the west side of Foley Boulevard. 

Street Reconstruction Project 19-3 – 3.3 miles of residential streets 

The Contractor for this project is Douglas-Kerr Underground, Inc. The Contractor's main contact is Ryan Kerr, who can be reached at 320-679-8937 (office) or 320-515-0046 (cell). Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).

Work during the week of July 8 includes preparation of streets in the Phase 1A area (Flintwood Street, Goldenrod Street, 114th Avenue, 116th Avenue, Evergreen Street, Evergreen Circle, and 117th Avenue) for asphalt base course pavement. Irrigation repairs in the Phase 1A area are tentatively scheduled. Permanent watermain construction is planned to begin Tuesday or Wednesday next week in the Phase 1B area (Bridgewater neighborhood consisting of Alder Street, Butternut Street, Cottonwood Street, 116th Avenue, 116th Lane, and 117th Avenue). 

Trail Reconstruction Project 19-11 – Wedgewood Trail, Nelson Park Trails, and Trackside Park Trails 

The Contractor for this project is Northwest Asphalt. The Contractor's main contact is John Hamers, who can be reached at 952-445-1003 (office) or 952-292-8471 (cell). Hafedh Hlel is the City’s project engineer/inspector, and can be contacted any time to respond to specific questions or concerns. Hafedh can be reached at 763-767-6412 (office) or 763-339-6128 (cell).

Construction during the week of July 8 includes work on final turf and concrete restorations on the Wedgewood Trail system, as well as Nelson and Trackside Parks. 

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-324-3114.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Watch our Videos!   

Watch the City’s street reconstruction videos to learn more about the process! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

View them here: www.coonrapidsmn.gov/843/Street-Reconstruction