Street Reconstruction Project 19-3 – 3.3 miles of residential streets
The Contractor for this project is Douglas-Kerr Underground, Inc. The Contractor's main contact is Ryan Kerr, who can be reached at 320-679-8937 (office) or 320-515-0046 (cell). Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work during the week of June 10 includes roadway section reconstruction within the Phase 1A area (Flintwood Street, Goldenrod Street, 114th Avenue, 116th Avenue, Evergreen Street, Evergreen Circle, and 117th Avenue). Utility replacements will take place within the Phase 1B area (north half of the Bridgewater neighborhood). Asphalt pavement reclamation is expected on the south half of the Bridgewater neighborhood where watermain pipe replacement is planned.