Street Reconstruction Project 19-3 – 3.3 miles of residential streets
The Contractor for this project is Douglas-Kerr Underground, Inc. The Contractor's main contact is Ryan Kerr, who can be reached at 320-679-8937 (office) or 320-515-0046 (cell). Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Construction is planned to begin the week of May 20. Initial work includes tree removals, curb removals and utility replacements in the Phase 1A area (Flintwood Street, Goldenrod Street, 114th Avenue, 116th Avenue, Evergreen Street, Evergreen Circle, and 117th Avenue). Property owners will be notified in advance of any temporary daytime water shut offs. Trees planned for removal will be marked with a pink “X”.