Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard
The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).
During the week of October 8, the Contractor plans to complete asphalt paving (weather pending) on Tuesday and Wednesday for 103rd and 104th Avenues. Other miscellaneous cleanup work will continue throughout the rest of the week. Once asphalt paving on 103rd and 104th Avenues takes place, this project will be considered substantially complete. If property owners identify any remaining issues, please contact the project inspector.