Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

During the week of September 24, the Contractor will place additional gravel material on 103rd Avenue, and prepare 103rd and 104th Avenues for eventual asphalt paving. Concrete driveway apron reestablishment is also planned to occur on both of these streets. New street sign installations and miscellaneous cleanup will take place throughout all segments of the project next week.

Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard   

The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

During the week of September 24, the Contractor plans to apply pavement markings and reinstall residential mailboxes in Area 3. Any remaining asphalt paving carried over from the week of September 17 will also take place. 

Egret Boulevard Watermain Reconstruction Project 18-7 – Watermain replacement along Egret Boulevard from Coon Rapids Boulevard Service Road to 99th Avenue   

The Contractor for this project is Dave Perkins Contracting, Inc. The Contractor's 24-hour emergency contacts are Rene Perkins at 612-363-6459 and John Acman at 320-224-0048. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

Final watermain connection work was completed during the week of September 17. Due to heavy rain activity this week, remaining surface restorations are now expected to be complete by the week of October 1.

Sidewalk Expansion Improvement Project 17-19 – Construction of miscellaneous sidewalk segments along Coon Rapids Boulevard, Dogwood Street, and 115th Avenue   

The Contractor for this project is Ti-Zack Concrete, Inc. The Contractor's 24-hour emergency contacts are Jim Leary at 612-309-4260 and Cory Johnson-Roe at 507-262-0913. Alex Wiebe is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell) or 763-767-6412 (office).

Due to delays caused by private utility conflicts and heavy rains this week, work on the remaining sidewalk gap to be filled under this project (located at 2669 Coon Rapids Boulevard) will be completed over the next two weeks. 

Miscellaneous Park and Trail Improvement Project 18-6 – Reconstruction of segments of Prairie Oaks Park, Burl Oaks Park, and Vineyards Park trails 

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contact is Herb Thielbar at 612-716-4214. Alex Wiebe is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell) or 763-767-6412 (office).

Heavy rains this week pushed remaining concrete and turf restoration activities to the week of September 24. 

Riverwalk Sanitary Sewer Rehabilitation Project 17-28 – Lining of 42-inch diameter City sewer pipe and associated manhole structures within the Riverwalk redevelopment area 

The Contractor for this project is Lametti & Sons, Inc. The Contractor's 24-hour emergency contacts are Jeffrey VanHoven at 651-248-3344 and David Lovas at 651-208-6517. Mike Ostendorf is the City’s Consultant designer, and can be contacted at 651-280-0679 to respond to any specific questions or concerns.

During the week of September 24, the Contractor plans to continue the manhole lining process, and complete installation of a new 42” segment of sewer pipe required near the existing Met Council lift station adjacent to Coon Rapids Boulevard Extension.

To accommodate the necessary work, Coon Rapids Boulevard Extension in the area of Vale Street will be closed to traffic beginning September 24. This road is expected to remain closed for up to three (3) weeks. 

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass  

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

A new watermain connection will be installed as part of the project, and work is anticipated to continue next week. The new pipe will provide continued water service to a residential neighborhood east of Hanson Boulevard during the grade separation project, as well as a permanent looped connection to that neighborhood into the future. Residents in the areas of 107th Avenue between Hummingbird and Killdeer Streets and 108th Lane west of Hanson Boulevard will be notified in advance of any temporary water shutoffs during the work.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Watch our Videos!   

To learn more about the street reconstruction process, watch the City’s new videos! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction