Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

During the week of September 17, the Contractor plans to install new curb and gutter on 103rd Avenue and 104th Avenue. In addition, concrete driveway apron re-establishments on these streets are planned.

Asphalt paving will take place on remaining streets within Area 4 (north of Egret Boulevard and east of Foley Boulevard).

Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard   

The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

During the week of September 17, the Contractor plans to complete asphalt paving on streets within Area 3 (Pheasant Ridge Drive, 114th Lane, 115th Avenue, Silverod Street, Undercliff Street, and Coon Rapids Boulevard Service Road). Mailboxes may also be reinstalled next week. 

Egret Boulevard Watermain Reconstruction Project 18-7 – Watermain replacement along Egret Boulevard from Coon Rapids Boulevard Service Road to 99th Avenue   

The Contractor for this project is Dave Perkins Contracting, Inc. The Contractor's 24-hour emergency contacts are Rene Perkins at 612-363-6459 and John Acman at 320-224-0048. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

The final watermain connection work is expected to be completed early next week. Remaining surface restorations will be completed shortly thereafter.

Sidewalk Expansion Improvement Project 17-19 – Construction of miscellaneous sidewalk segments along Coon Rapids Boulevard, Dogwood Street, and 115th Avenue   

The Contractor for this project is Ti-Zack Concrete, Inc. The Contractor's 24-hour emergency contacts are Jim Leary at 612-309-4260 and Cory Johnson-Roe at 507-262-0913. Alex Wiebe is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell) or 763-767-6412 (office).

During the week of September 17, work on the remaining sidewalk gap to be filled on this project (at 2669 Coon Rapids Boulevard) is expected to begin. 

Miscellaneous Park and Trail Improvement Project 18-6 – Reconstruction of segments of Prairie Oaks Park, Burl Oaks Park, and Vineyards Park trails 

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contact is Herb Thielbar at 612-716-4214. Alex Wiebe is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell) or 763-767-6412 (office).

Remaining concrete and turf restoration activities are expected to be complete next week. 

Riverwalk Sanitary Sewer Rehabilitation Project 17-28 – Lining of 42-inch diameter City sewer pipe and associated manhole structures within the Riverwalk redevelopment area 

The Contractor for this project is Lametti & Sons, Inc. The Contractor's 24-hour emergency contacts are Jeffrey VanHoven at 651-248-3344 and David Lovas at 651-208-6517. Mike Ostendorf is the City’s Consultant designer, and can be contacted at 651-280-0679 to respond to any specific questions or concerns.

During the week of September 17, the Contractor plans begin the manhole lining process. The 42-inch pipe lining process will take place after the sewer manhole lining is complete.

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass  

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

A new watermain connection will be installed as part of the project, and work is anticipated to continue next week. The new pipe will provide continued water service to a residential neighborhood east of Hanson Boulevard during the grade separation project, as well as a permanent looped connection to that neighborhood into the future. Residents in the areas of 107th Avenue between Hummingbird and Killdeer Streets and 108th Lane west of Hanson Boulevard will be notified in advance of any temporary water shutoffs during the work.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Watch our Videos!   

To learn more about the street reconstruction process, watch the City’s new videos! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction