Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

During the week of August 20, the Contractor plans to continue driveway and boulevard restorations as well as irrigation repairs on streets within Area 4 (streets located generally east of Foley Boulevard and south of Northdale Boulevard). Asphalt pavement reclamation is expected on Area 4 streets that have not been reclaimed yet, as well as on 103rd Avenue and 104th Avenue on the east side of Foley Boulevard.

New asphalt paving is anticipated on segments of 107th Lane, 108th Avenue, 109th Lane, Butternut Street, Cottonwood Street and Dogwood Street (all within Area 4). 

Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard   

The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

During the week of August 20, the Contractor plans to work on irrigation, driveway, and boulevard restorations on streets within Area 3 (Pheasant Ridge Drive, 114th Lane, 115th Avenue, Silverod Street, Undercliff Street, and Coon Rapids Boulevard Service Road). 

Egret Boulevard Watermain Reconstruction Project 18-7 – Watermain replacement along Egret Boulevard from Coon Rapids Boulevard Service Road to 99th Avenue   

The Contractor for this project is Dave Perkins Contracting, Inc. The Contractor's 24-hour emergency contacts are Rene Perkins at 612-363-6459 and John Acman at 320-224-0048. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

As work was progressing on this project during the week of July 23, there was a delay with the northernmost pipe connection on Egret Boulevard near the City well station. To resolve this connection delay, it was determined that additional custom parts which must be fabricated and shipped to the job site are required. Based on production and delivery of the parts, remaining watermain connection work and surface restorations are expected to be completed during the weeks of August 27 and September 3. 

Sidewalk Expansion Improvement Project 17-19 – Construction of miscellaneous sidewalk segments along Coon Rapids Boulevard, Dogwood Street, and 115th Avenue   

The Contractor for this project is Ti-Zack Concrete, Inc. The Contractor's 24-hour emergency contacts are Jim Leary at 612-309-4260 and Cory Johnson-Roe at 507-262-0913. Alex Wiebe is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell) or 763-767-6412 (office).

During the week of August 20, the Contractor expects to begin work on sidewalk segments planned for construction at 2121 Coon Rapids Boulevard (Neil’s Auto Body), 3237 Coon Rapids Boulevard (WCCO Tower), and 298 Coon Rapids Boulevard south of 93rd Avenue. Work will continue on sidewalk construction along Dogwood Street and 115th Avenue.  

Miscellaneous Park and Trail Improvement Project 18-6 – Reconstruction of segments of Prairie Oaks Park, Burl Oaks Park, and Vineyards Park trails 

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contact is Herb Thielbar at 612-716-4214. Alex Wiebe is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell) or 763-767-6412 (office).

During the week of August 20, the Contractor will work on restoration activities along the Burl Oaks and Prairie Oaks trail segments. Removals and grading operations will take place on the Vineyards Park trail system. 

Riverwalk Sanitary Sewer Rehabilitation Project 17-28 – Lining of 42-inch diameter City sewer pipe and associated manhole structures within the Riverwalk re-development area 

The Contractor for this project is Lametti & Sons, Inc. The Contractor's 24-hour emergency contacts are Jeffrey VanHoven at 651-248-3344 and David Lovas at 651-208-6517. Mike Ostendorf is the City’s Consultant designer, and can be contacted at 651-280-0679 to respond to any specific questions or concerns.

During the week of August 20, the Contractor will continue setting up the temporary bypass network necessary to re-route sewer flows for the planned 42-inch sewer pipe lining. 

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass  

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Watch our Videos!   

To learn more about the street reconstruction process, watch the City’s new videos! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction