Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard
The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
During the week of August 6, the Contractor plans to complete hydrant and valve replacements, as well as curb and gutter removals within Area 3 (Pheasant Ridge Drive, 114th Lane, 115th Avenue, Silverod Street, Undercliff Street, and Coon Rapids Boulevard Service Road). Utility replacements will require daytime water shut offs (9:00 a.m. to 4:00 p.m.). Residents will be notified of any water shut offs at least 24 hours in advance, with the exception of emergency situations.