Construction Updates

To sign up for email notifications of these weekly updates, click Notify Me and select “Construction Updates.”

Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

During the week of July 30, the Contractor plans to continue concrete and asphalt driveway restorations and hydrant/valve replacements within Area 4 (streets located generally north of Egret Boulevard and east of Foley Boulevard). In addition, boulevard restorations and irrigation repairs are planned for streets within Area 4. 

Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard   

The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

During the week of July 30, the Contractor plans to perform concrete and driveway saw-cutting and concrete curb removals on streets within Area 3 (Pheasant Ridge Drive, 114th Lane, 115th Avenue, Silverod Street, Undercliff Street, and Coon Rapids Boulevard Service Road). Hydrant and valve replacements may begin toward the end of next week. These utility replacements will require daytime water shut offs (9:00 a.m. to 4:00 p.m.). Residents will be notified of any water shut offs at least 24 hours in advance. 

Egret Boulevard Watermain Reconstruction Project 18-7 – Watermain replacement along Egret Boulevard from Coon Rapids Boulevard Service Road to 99th Avenue   

The Contractor for this project is Dave Perkins Contracting, Inc. The Contractor's 24-hour emergency contacts are Rene Perkins at 612-363-6459 and John Acman at 320-224-0048. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

During the week of July 30, the Contractor plans to complete remaining asphalt and boulevard restoration work. The project is anticipated to be complete by the end of the week. 

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass  

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Watch our Videos!   

To learn more about the street reconstruction process, watch the City’s new videos! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction