Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard
The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
Please note the Contractor plans to perform grading of the reclaimed roadway base on streets within Area 2 on Saturday, July 14. This work is scheduled to take place between 8:00 a.m. and 6:00 p.m.
During the week of July 16, grading and preparation of the reclaimed roadway base is expected to continue for streets within Area 2 (118th Lane, 119th Avenue, 119th Lane, 120th Avenue, 121st Avenue, Eidelweiss Street, and Jonquil Street).