Construction Updates

Construction Updates for July 6, 2018

To sign up for email notifications of these weekly updates, click Notify Me and select “Construction Updates.”

Property owners within this year’s street reconstruction project areas should have received notification letters between the weeks of May 7 and 14 with project and schedule information. If you would like a copy, please email Engineering@coonrapidsmn.gov or call 763-767-6479.

Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).
During the week of July 9, the Contractor plans to complete asphalt driveway restorations and remaining topsoil and boulevard seeding within Area 3 (streets west of Foley Boulevard). Concrete removals and hydrant and valve replacements are expected to begin on certain streets within Area 4 (streets located generally north of Egret Boulevard including 107th Lane, 108th Avenue, segments of Cottonwood Street, and 109th Lane).

Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard   

The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
During the week of July 9, remaining irrigation repairs and topsoil placement, as well as any remaining concrete and asphalt driveway restorations and tri-section work, is planned for Area 2 (118th Lane, 119th Avenue, 119th Lane, 120th Avenue, 121st Avenue, Eidelweiss Street, and Jonquil Street). Asphalt reclamation for Area 2 is planned for Thursday and Friday (July 12 and 13) next week.

Egret Boulevard Watermain Reconstruction Project 18-7 – Watermain replacement along Egret Boulevard from Coon Rapids Boulevard Service Road to 99th Avenue 

The Contractor for this project is Dave Perkins Contracting, Inc. The Contractor's 24-hour emergency contacts are Rene Perkins at 612-363-6459 and John Acman at 320-224-0048. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).
During the week of July 9, the Contractor plans to complete the installation of the new directionally drilled watermain pipe. In addition, hydrant and valve replacements, as well as water service re-connections are expected.

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass 

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.
To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Watch our Videos!  

To learn more about the street reconstruction process, watch the City’s new videos! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.
Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction