Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard
The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
During the week of July 2, irrigation repairs and topsoil placement, as well as remaining concrete driveway and tri-section work, is planned for Area 2 (118th Lane, 119th Avenue, 119th Lane, 120th Avenue, 121st Avenue, Eidelweiss Street, and Jonquil Street). No work will take place on Wednesday, July 4.
Placement of the final lift of asphalt wear course is planned for Silverod Street, Marigold Street, and 129th Avenue on Tuesday, July 3.