Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard
The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
During the week of June 25, paving activities are planned for Area 1 (129th Avenue, Marigold Street, Lily Street, 131st Lane, and Silverod Street).
Note: The Contractor plans to continue paving on Lily Street, 131st Lane, and Silverod Street in Area 1 on Saturday, June 23. No work will begin before 8 a.m.
In Area 2 (118th Lane, 119th Avenue, 119th Lane, 120th Avenue, 121st Avenue, Eidelweiss Street, and Jonquil Street), the Contractor plans to complete installation of new concrete curb and gutter and begin restoration work.