Property owners within this year’s street reconstruction project areas should have received notification letters between the weeks of May 7 and 14 with project and schedule information. If you would like a copy, please email Engineering@coonrapidsmn.gov or call 763-767-6479.

Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

During the week of June 18, the Contractor plans to continue completion of remaining curb and asphalt/concrete driveway installations in Area 2 (104th Lane, 105th Avenue, 105th Lane, 106th Avenue, and Goldenrod Street east of Foley Boulevard). Topsoil placement, and possibly seeding, is also planned for Area 2. Fire hydrant and valve replacements are scheduled to begin in Area 3 (streets west of Foley Boulevard) next week.

Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard   

The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

During the week of June 18, pavement reclamation and completion of remaining turf restoration is planned for Area 1 (131st Lane, Silverod Street, 129th Avenue, Marigold Street, and Lily Street). In Area 2 (118th Lane, 119th Avenue, 119th Lane, 120th Avenue, 121st Avenue, Eidelweiss Street, and Jonquil Street), the Contractor plans to complete remaining hydrant and valve replacements, and begin installation of new curb and gutter.

Anoka County Project – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). The County’s Contractor for this project is C.S McCrossan. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Watch our Videos!

To learn more about the street reconstruction process, watch the City’s new videos! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction

Report It