Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard
The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).
Note: The Contractor plans to perform new curb and driveway apron replacements in Area 2 (104th Lane, 105th Avenue, 105th Lane, 106th Avenue, and Goldenrod Street east of Foley Boulevard) on Saturday, June 9. No work will begin before 8 a.m., and access to businesses and properties along these streets should not be affected.
During the week of June 11, the Contractor plans to complete any remaining concrete curb and driveway installations in Area 2 (104th Lane, 105th Avenue, 105th Lane, 106th Avenue, and Goldenrod Street east of Foley Boulevard). New asphalt paving is planned to occur on Cottonwood Street south of 101st Avenue, as well as on 102nd Lane east of Foley Boulevard. Irrigation repairs are also scheduled for next week.