Street Reconstruction Project 18-2 – 4 miles of residential streets south of Coon Rapids Boulevard near Round Lake Boulevard and streets between Northdale Boulevard and Crooked Lake Boulevard
The Contractor for this project is Northwest Asphalt, Inc. The Contractor's 24-hour emergency contacts are John Lenarz at 952-220-0684 and John Hamers at 952-292-8470. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
Note: The Contractor plans to perform new curb and driveway apron replacements in areas along 129th Avenue, Marigold Street, 131st Lane, and Silverod Street on Saturday, June 2. No work will begin before 8 a.m., and access to businesses and properties along these streets should not be affected.
During the week of June 4, the Contractor plans to complete curb and driveway apron replacements, topsoil backfill placement, seeding, and irrigation repairs in Area 1 (131st Lane, Silverod Street, 129th Avenue, Marigold Street, and Lily Street). Manhole and valve casting adjustments, as well as curb removals, are planned to begin in Area 2 (118th Lane, 119th Avenue, 119th Lane, 120th Avenue, 121st Avenue, Eidelweiss Street, and Jonquil Street). Hydrant and valve replacements are also planned to begin next week on 118th Lane.