Street Reconstruction Project 18-1 – 4.7 miles of residential streets on the east and west sides of Foley Boulevard, from near Highway 10 to south of Northdale Boulevard.
The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contacts are Herb Thielbar at 612-716-4214 and Jeff Wunderlich at 612-282-5039. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).
During the week of May 29, the Contractor plans to complete curb removals in Area 2 (104th Lane, 105th Avenue, 105th Lane, 106th Avenue, and Goldenrod Street east of Foley Boulevard). In addition, the Contractor will work on hydrant and gate valve replacements in this area.
Topsoil and seeding, as well as asphalt driveway apron replacements, will be performed next week in Area 1 (102nd Lane and Cottonwood Street). New curb is planned for 104th Lane and 105th Avenue in Area 2. No work will take place on May 28.