Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

This project is now complete. The Contractor (Park Construction) will continue to perform remaining clean-up and restorations, including seeding and irrigation repairs for the next few weeks. Please contact Jason Huebscher (the City’s full-time project inspector) at 612-709-2704 (cell) if there are any questions or issues that need to be addressed. 

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

During the week of October 9, the Contractor plans to pave the remaining asphalt base course on the middle two lanes of 101st Avenue between Foley Boulevard and University Avenue.  Traffic will then be shifted back to the two inside lanes so remaining cleanup work can take place in the boulevard areas.

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

During the week of October 9, the Contractor will pave streets in the phase 3 area (Butternut, Cottonwood, Dogwood, Flintwood, Ilex, Holly, Juniper, Kumquat, and Larch Streets – streets adjacent to 121st Avenue, as well as 123rd Avenue east of Foley Boulevard).  Notices (handouts on/near front doors) will be provided to affected residents in advance of the paving operations.

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

This project is now complete. The Contractor (North Valley) will continue to perform remaining clean-up and restorations, including seeding and irrigation repairs for the next few weeks. Please contact Zach Pfieffer (the City’s full-time project inspector) at 612-710-8243 (cell) if there are any questions or issues that need to be addressed. 

Report It
Powered by CivicSend - A product of CivicPlus