Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods
The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).
During the week of October 2, the Contractor will continue work in the phase 3 area streets (Butternut, Cottonwood, Dogwood, Flintwood, Ilex, Holly, Juniper, Kumquat, and Larch Streets – streets adjacent to 121st Avenue, as well as 123rd Avenue east of Foley Boulevard). Work shall include irrigation restorations, boulevard restorations, and miscellaneous concrete sidewalk installations. Paving of the phase 3 streets is now anticipated late the week of October 9 or early the week of October 16.