Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods
The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).
Note: The Contractor plans to continue ancillary boulevard restorations in the phase 3 area on Saturday, September 26, 2017. No impacts to residential driveways are anticipated with this Saturday work.
During the week of September 25, the Contractor will continue work in the phase 3 area streets (Butternut, Cottonwood, Dogwood, Flintwood, Ilex, Holly, Juniper, Kumquat, and Larch Streets – streets adjacent to 121st Avenue, as well as 123rd Avenue east of Foley Boulevard). Work shall include irrigation restorations, boulevard restorations, and miscellaneous concrete sidewalk installations. The Contractor also plans to reclaim Butternut Street, Cottonwood Street, Dogwood Street, Flintwood Street/Circle and 122nd Avenue, preparing to pave these streets possibly by the end of next week.