Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

Note: Weather pending, the Contractor plans to pave the phase 3 area streets on Saturday, September 16, 2017. Property owners will be notified in advance of any driveway access restrictions.  

For the week of September 18, the Contractor will wrap up any remaining asphalt paving, as well as perform miscellaneous clean-up restorations and signing/striping activities.  

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

Note: The Contractor plans to perform grading and restoration work on 101st Avenue on Saturday, September 16, 2017. Property owners will be notified in advance of any driveway access restrictions.  

During the week of September 18, the Contractor will switch traffic to stage 2 on 101st Avenue, and perform miscellaneous removals and asphalt reclamation. Painting/striping is planned for Shenandoah Boulevard next week as well.  

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

Note: Weather pending, the Contractor will continue working on curb and gutter installations in the phase 3 area on Saturday, September 16, 2017. Property owners will be notified in advance of any driveway access restrictions.

During the week of September 18, the Contractor will continue remaining installations of curb and gutter on phase 3 area streets (Butternut, Cottonwood, Dogwood, Flintwood, Ilex, Holly, Juniper, Kumquat, and Larch Streets – streets adjacent to 121st Avenue, as well as 123rd Avenue east of Foley Boulevard). Curb was delayed on these streets the week of September 11 due to Contractor scheduling conflicts. 

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

For the week of September 18, the Contractor will perform miscellaneous clean up and restoration work on 126th Avenue, 127th Avenue, 127th Lane, Holly Street, and Juniper Street (streets near Bunker Hills Park). 