Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Dakotah Street Reconstruction adjacent to Mercy Hospital

Dakotah Street from Coon Rapids Boulevard to approximately 600-feet south is being reconstructed in conjunction with the Mercy Hospital expansion. The Contractor is Bolander Construction.

At this time, the road is fully open to traffic, and completion of remaining street reconstruction work is currently scheduled for the week of August 14.

Please note: Final wear course paving is scheduled on Saturday, August 19 from 8 a.m. to 6 p.m.   

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

For the week of August 14, asphalt paving is scheduled to take place on Monday and Tuesday for phase 1 and 2 streets. On Monday, paving is planned on 104th Avenue, 104th Lane, Alder Street, Butternut Street, and the University Avenue Service Road. On Tuesday, paving activities will include Dogwood Street and 105th Avenue.
 
Please note: On Saturday, August 12, the Contractor will perform miscellaneous casting adjustments and grading work in advance of paving operations in the phase 1 and 2 areas.

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

During the week of August 14, watermain construction work will continue on 101st Avenue, which will include service extensions and re-establishments. The Contractor will also perform storm sewer catch basin replacements on 101st Avenue and Shenandoah Boulevard. 

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

During the week of August 14, remaining concrete work is scheduled on 123rd Avenue, 120th Lane, Ilex Street, and Juniper Street. The Contractor also plans to perform boulevard restorations and irrigation repairs. 

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

For the week of August 14, asphalt paving is anticipated to occur on 93rd Avenue and 93rd Lane. Valve and hydrant replacement work will continue on Golf View (127th Lane and Juniper Street) and Highland Manor streets (126th and 127th Avenue and Holly Street). 

Trail Construction Project 17-10 – Coon Rapids Boulevard Extension

The Contractor for this project is Forest Lake Contracting. The Contractor's 24-hour emergency contact is Wade Kosman at 651-248-4707. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

For the week of August 14, the Contractor will patch driveways and perform miscellaneous turf restorations along the new trail segment. 

Trail Construction Project 17-11 – Coon Rapids Boulevard / Egret Boulevard Trail

The Contractor for this project is Barber Construction. The Contractor's 24-hour emergency contact is Jerry Barber at 612-709-9227. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

For the week of August 14, the Contractor will complete concrete work along Egret Boulevard, as well as perform miscellaneous turf restorations along the new trail segments. 