Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard
The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).
During the week of August 7, watermain construction work will continue on 101st Avenue to perform a watermain pipe connection to University Avenue.
Please note: on Monday and Tuesday, August 7 and 8, work is scheduled during overnight hours (7 p.m. to 6 a.m.) on University Avenue at 101st Avenue.
Also, curb removals are anticipated on Shenandoah Boulevard. Pending progress, pavement reclamation may occur as well.