Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekl

Dakotah Street Reconstruction adjacent to Mercy Hospital

Dakotah Street from Coon Rapids Boulevard to approximately 600-feet south is being reconstructed in conjunction with the Mercy Hospital expansion. The Contractor is Bolander Construction. At this time, the road is fully open to traffic, and completion of remaining street reconstruction work is currently scheduled between August 7 and August 18.

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

For the week of July 31, remaining topsoil and seeding placement and driveway restorations are scheduled for all streets currently under construction. Driveway aprons will be restored on 104th Lane, Alder Street, and Butternut Street. Preparation for asphalt paving will also take place on each street currently under construction. We anticipate the same streets will receive new asphalt the week of August 7. 

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

Please note: Asphalt base paving on 121st Avenue is planned for Saturday, July 29. The work will take place from 8:00 a.m. to approximately 7:00 p.m. This road will be open to local traffic only during the paving process.

During the week of July 31, hydrant, valve, and ancillary storm sewer catch basin replacement work is scheduled on Shenandoah Boulevard. Permanent watermain installations on 101st Avenue will continue throughout next week. 

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

During the week of July 31, miscellaneous hand-formed curb and sidewalk work will take place on 123rd Avenue. Additionally, machine-poured curb will be installed on 120th Lane, Ilex Street, and Juniper Street. The Contractor may begin work on catch basin replacements on 123rd Avenue. 

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

For the week of July 31, the Contractor will restore boulevard areas on 93rd Avenue and 93rd Lane, as well as grade the road base in preparation for asphalt paving. Miscellaneous hydrant and valve replacements are anticipated to begin midweek on the Golf View (127th Lane and Juniper Street) and Highland Manor streets (126th and 127th Avenue and Holly Street). 

Trail Construction Project 17-10 – Coon Rapids Boulevard Extension

The Contractor for this project is Forest Lake Contracting. The Contractor's 24-hour emergency contact is Wade Kosman at 651-248-4707. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

Throughout the week of July 31, the Contractor will work on finish grading the trail base and side slopes. 

Trail Construction Project 17-11 – Coon Rapids Boulevard / Egret Boulevard Trail

The Contractor for this project is Barber Construction. The Contractor's 24-hour emergency contact is Jerry Barber at 612-709-9227. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

For the week of July 31, the Contractor plans to continue work on the big block retaining wall system located on the west side of Egret Boulevard between Coon Rapids Boulevard Service Road and the City well station. 

Report It
Powered by CivicSend - A product of CivicPlus