Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue
The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Nate at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).
For the week of July 17, utility work within the phase 1 and 2 areas is anticipated to be complete by mid-week. Excavation, subgrade, and gravel placement will occur on 104th Avenue and 104th Lane. Mailbox restorations are expected throughout the areas currently under construction. New curb and gutter installations may occur on 104th Lane, Alder Street, and Butternut Street.