Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Dakotah Street Reconstruction adjacent to Mercy Hospital

Dakotah Street from Coon Rapids Boulevard to approximately 600-feet south is being reconstructed in conjunction with the Mercy Hospital expansion. The Contractor is Bolander Construction. At this time, the road is fully open to traffic, and completion of remaining street reconstruction work is on hold until August 2017.  

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

For the week of July 10, the Contractor plans to complete the topsoil placement and seeding work needed on Dogwood Street and 105th Avenue. Water service re-establishments are planned for 104th Lane. Curb and gutter installations are expected on 104th Avenue. In addition, concrete driveway aprons are planned to be poured on 104th Avenue. Fine grading of gravel base in preparation for paving is anticipated on Dogwood Street by the end of next week. 

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

For the week of July 10, the Contractor plans to complete installation of concrete driveways and valley gutters along 121st Avenue. Pavement reclamation of 121st Avenue is planned for Thursday, July 13. 

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

During the week of July 10, hydrant replacement work is scheduled at 120th Lane and Ilex Street. Curb removals are anticipated to begin on the phase two streets consisting of 123rd Avenue, 120th Lane, Ilex Street, and Juniper Street. 

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

For the week of July 10, the Contractor anticipates reclaiming Killdeer, Ibis, and Grouse Streets, 129th Circle, and 121st Lane/Osage Street (west of Shenandoah Boulevard). Asphalt paving on some of these street segments is planned for by the end of next week. Residents will be notified in advance of paving operations. Curb removals will continue on 93rd Lane. 

Trail Construction Project 17-10 – Coon Rapids Boulevard Extension

The Contractor for this project is Forest Lake Contracting. The Contractor's 24-hour emergency contact is Wade Kosman at 651-248-4707. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

For the week of July 10, the Contractor plans to continue with topsoil stripping and muck exaction required along Coon Rapids Boulevard Extension. Pavement reclamation is anticipated on the service road connection between Quince Street and Palm Street. The Contractor may begin work on a portion of the storm sewer culvert installations by the end of next week. 

Trail Construction Project 17-11 – Coon Rapids Boulevard / Egret Boulevard Trail

The Contractor for this project is Barber Construction. The Contractor's 24-hour emergency contact is Jerry Barber at 612-709-9227. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

For the week of July 10, the Contractor plans to install gravel base in preparation for the new trail along Egret Boulevard, and to complete modular block wall installations along both Coon Rapids Boulevard and Egret Boulevard. Some portions of the trail may be paved along Coon Rapids Boulevard and the south portion of Egret Boulevard by the end of next week. 

Report It
Powered by CivicSend - A product of CivicPlus