Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

Dakotah Street Reconstruction adjacent to Mercy Hospital

Dakotah Street from Coon Rapids Boulevard to approximately 600-feet south is being reconstructed in conjunction with the Mercy Hospital expansion. The Contractor is Bolander Construction. At this time, the road is fully open to traffic, and completion of remaining street reconstruction work is on-hold until August 2017.  

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

For the week of June 26, the Contractor plans to place topsoil in the boulevards along Dogwood Street. Subgrade excavation and gravel placement will take place on 104th Avenue. Miscellaneous concrete installations are planned to occur at the intersections of Dogwood Street from 104th Avenue north to 105th Avenue. Temporary watermain construction will take place on 104th Lane, after which the Contractor will begin installation of the permanent watermain system in the same area. 

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

The Contractor plans to complete curb removals on 121st Avenue during the week of June 26. In addition, replacements of concrete valley gutters are planned for the north side of 121st Avenue.  

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

During the week of June 26, it’s anticipated that asphalt paving will occur in the following areas: Norway Street, Magnolia Street, Larch Circle, Holly Street north of 123rd Avenue, and Goldenrod Circle. 

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

Curb and gutter installations are planned to continue on Killdeer, Ibis, and Grouse Streets the week of June 26. The same work will also occur on Linnet Circle, as well as 121st Lane and Osage Street (both west of Shenandoah Boulevard). 

Trail Construction Project 17-10 – Coon Rapids Boulevard Extension

The Contractor for this project is Forest Lake Contracting. The Contractor's 24-hour emergency contact is Wade Kosman at 651-248-4707. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

Work on this project is anticipated to begin on July 5, 2017. 

Trail Construction Project 17-11 – Coon Rapids Boulevard / Egret Boulevard Trail

The Contractor for this project is Barber Construction. The Contractor's 24-hour emergency contact is Jerry Barber at 612-709-9227. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).

Work on this project is anticipated to begin the week of June 26, 2017. Initial project work will focus only on the reconstruction of the Coon Rapids Boulevard segment of trail. 

Report It