Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250.
To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly
|
|
|
|
Wilderness – Bunker Hills Trail Extension (Project 17-9)The Contractor for this project is Barber Construction. Work on the new trail segment from Avocet Street to south of the Dog Park is currently underway. The project is scheduled to be complete by June 23, 2017.
|
|
|
|
Crescent Ponds 9th Addition (Project 17-18) – Southwest corner of Main Street and University AvenueThe Contractor for this project is LaTour Construction. Work on public infrastructure (watermain, sanitary sewer, storm sewer, and street) for this new 19-lot, single-family development is currently underway.
For the week of June 19, the Contractor plans to complete the asphalt paving and boulevard grading on the new cul-de-sac. The infrastructure project (not including new home construction) is scheduled to be complete by June 30, 2017.
|
|
|
|
Dakotah Street Reconstruction adjacent to Mercy HospitalOver the next few months, Dakotah Street from Coon Rapids Boulevard to approximately 600-feet south will be reconstructed in conjunction with the Mercy Hospital expansion. The Contractor for this work is Bolander Construction.
Work during the week of June 19 includes asphalt paving on the west side of Dakotah Street.
|
|
|
|
Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st AvenueThe Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).
Curb and gutter installation is expected to continue the week of June 19 on Dogwood Street and 105th Avenue. Work will also continue on the water services along 104th Avenue. Boulevard and sprinkler restorations are anticipated on Dogwood Street and 105th Avenue after completion of curb and gutter work.
|
|
|
|
Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah BoulevardThe Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).
Beginning Tuesday, June 20, curb installations originally scheduled for the week of June 12 will take place on the south side of 121st Avenue.
|
|
|
|
Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).
During the week of June 19, it’s anticipated that pavement reclamation and excess gravel removals will occur in the following areas: Norway Street, Magnolia Street, Larch Circle, Holly Street north of 123rd Avenue, and Goldenrod Circle.
|
|
|
|
Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
Curb and gutter installations are planned for Killdeer, Ibis, and Grouse Streets the week of June 19. Also, hydrant and valve replacements and curb removals are scheduled for 121st Lane and Osage Street (both west of Shenandoah Boulevard). New curb installations may also take place on Linnet Circle. Storm sewer pipe and watermain work will continue on 93rd Lane and 93rd Avenue.
|
|
|
|
Trail Construction Project 17-10 – Coon Rapids Boulevard ExtensionThe Contractor for this project is Forest Lake Contracting. The Contractor's 24-hour emergency contact is Wade Kosman at 651-248-4707. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).
Work on this project is anticipated to begin after July 4, 2017.
|
|
|
|
Trail Construction Project 17-11 – Coon Rapids Boulevard / Egret Boulevard TrailThe Contractor for this project is Barber Construction. The Contractor's 24-hour emergency contact is Jerry Barber at 612-709-9227. Alex Wiebe is the project inspector, and can be contacted any time to respond to specific questions or concerns. Alex can be reached at 612-716-3141 (cell).
Work on this project is anticipated to begin the week of June 26, 2017.
|
|
|
|
|