Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250. Mike Carpenter with Bolton & Menk is the City’s project inspector, and can be reached at 651-968-6924.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

This segment of Foley Boulevard is closed to thru traffic until early July (weather pending). The road will remain open for local traffic, emergency vehicles and for accessibility to area businesses. 

Wilderness – Bunker Hills Trail Extension (Project 17-9)

The Contractor for this project is Barber Construction. Work on the new trail segment from Avocet Street to south of the Dog Park is currently underway. The project is scheduled to be complete by June 23, 2017. 

Crescent Ponds 9th Addition (Project 17-18)

The Contractor for this project is LaTour Construction. Work on public infrastructure (watermain, sanitary sewer, storm sewer, and street) for this new 19-lot, single-family development is planned to begin the week of May 30. The infrastructure project (not including new home construction) is scheduled to be complete by June 30, 2017. 

Dakotah Street Reconstruction adjacent to Mercy Hospital

Over the next few months, Dakotah Street from Coon Rapids Boulevard to approximately 600-feet south will be reconstructed in conjunction with the Mercy Hospital expansion. The Contractor for this work is Bolander Construction. Work during the week of May 30 includes storm sewer pipe construction, street excavation and grading. 

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

During the week of May 30, valve and hydrant replacements are anticipated at 106th Avenue and Dogwood Street, as well as 105th Avenue and Dogwood Street. Storm sewer work will continue along Dogwood Street. The Contractor may begin work on the new watermain replacements on 104th Avenue and 104th Lane. Concrete curb and gutter is planned for the University Avenue Service Road. 

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

During the week of May 30, work will include storm sewer reconstruction on 121st Avenue, and remaining concrete sidewalk and tri-section replacements. 

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

Work has yet to begin on this project. It’s anticipated that removals will begin on the following streets in the next couple of weeks: Norway Street, Magnolia Street, Larch Circle, Holly Street north of 123rd Avenue, and Goldenrod Circle. All work on this project will be completed by mid-September.

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

During the week of May 30, 133rd Avenue, Eidelweiss Street, Flora Street, Gladiola Street, and 132nd Avenue are anticipated to be reclaimed. Concrete curb and gutter installation is expected on 121st Lane. Removals are planned for Riverdale Drive.