Street Reconstruction Update

To sign up for email notifications of these weekly updates, click Notify Me and select “Street Reconstruction Updates.”

Anoka County Project – Foley Boulevard Reconstruction (Egret to Northdale)

Foley Boulevard is a County road in Coon Rapids. The County’s Contractor for this project is Forest Lake Contracting, Inc. Harry Grams is the County’s Construction Supervisor, and can be contacted at 763-862-4250. Mike Carpenter with Bolton & Menk is the City’s project inspector, and can be reached at 651-968-6924.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly

This segment of Foley Boulevard is closed to thru traffic until early July (weather pending). The road will remain open for local traffic, emergency vehicles and for accessibility to area businesses. 

Wilderness – Bunker Hills Trail Extension (Project 17-9)

The Contractor for this project is Barber Construction. Work on the new trail segment from Avocet Street to south of the Dog Park is currently underway. The project is scheduled to be complete by June 23, 2017. 

Street Reconstruction Project 17-1 – Neighborhood Streets between Dogwood Street and University Avenue south of Egret Boulevard and north of 101st Avenue

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).

During the week of May 22, removal work is planned to continue on the following streets: 104th Lane, 104th Avenue, Alder Street, University Avenue Service Road, Dogwood Street, 105th Avenue, and Butternut Street between 104th Lane and 105th Avenue. The Contractor will also perform tree removals on 104th Avenue and 104th Lane in advance of watermain pipe replacement. Trees planned for removal have been marked with a white “X”. Residents have been notified of these pending tree removals via US Mail.

Setup for the temporary watermain system on 104th Avenue and 104th Lane will also continue. Ancillary hydrant and watermain connection work is planned to occur on Dogwood Street between 101st Avenue and 102nd Lane.

Street Reconstruction Project 17-2 – 101st Avenue, 121st Avenue, and Shenandoah Boulevard

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Tom Breyfogle at 612-360-9295. Andy Evans with Hakanson Anderson is the full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andy can be reached at 612-716-3788 (cell).

During the week of May 22, removal work is planned to continue on 121st Avenue. In addition, tree removals are planned to occur along 101st Avenue in advance of watermain work scheduled to begin in July. 

Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).

During the week of May 22, removal work is planned to continue on the following streets: Norway Street, Magnolia Street, Larch Circle, Holly Street north of 123rd Avenue, and Goldenrod Circle.

Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids 

The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).

During the week of May 22, removal work is planned to continue on the following streets: Riverdale Drive, 133rd Avenue, Eidelweiss Street, Flora Street, Gladiola Street, 132nd Avenue, and 121st Lane west of Crooked Lake Boulevard.

Valve and hydrant replacements will take place during daytime hours on 121st Lane beginning on May 22, and on Riverdale Drive during overnight hours Thursday night/Friday morning next week. Businesses along Riverdale Drive will be notified in advance of any water shut downs required to perform these repairs.

Report It