Street Reconstruction Project 17-4 – Various Local Streets throughout Coon Rapids
The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Zach Pfieffer is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243 (cell).
During the week of May 22, removal work is planned to continue on the following streets: Riverdale Drive, 133rd Avenue, Eidelweiss Street, Flora Street, Gladiola Street, 132nd Avenue, and 121st Lane west of Crooked Lake Boulevard.
Valve and hydrant replacements will take place during daytime hours on 121st Lane beginning on May 22, and on Riverdale Drive during overnight hours Thursday night/Friday morning next week. Businesses along Riverdale Drive will be notified in advance of any water shut downs required to perform these repairs.