Street Reconstruction Update

MSA Street Reconstruction (Project 16-1 – Evergreen Boulevard Area)

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Derick Sonnenberg at 612-791-4350. Jon Halter with Hakanson Anderson is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jon can be reached at 612-282-0725.

Please note that all work indicated is weather pending and Subject to Change.

Final signing and striping activities are scheduled for the week of October 31. The Contractor will work on final punch list items over the next couple of weeks.

MSA Street Reconstruction (Project 16-2 – Mississippi Boulevard Area)

The Contractor for this project is Forest Lake Contracting, Inc. The Contractor's 24-hour emergency contact is Tim Matteson at 651-248-4708. Ron Sample is the City's full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874.

Please note that all work indicated is weather pending and Subject to Change.

Remaining driveway re-establishments and boulevard and irrigation restorations along Mississippi Boulevard are scheduled the week of October 31. The Contractor has tentatively scheduled the final lift of asphalt paving to begin on November 3. Final seeding, signing and striping are planned for the week of November 7.

Please contact the City if you have any questions about how to coordinate remaining irrigation repairs as you schedule your system blow out in preparation for winter. 