Street Reconstruction Update

MSA Street Reconstruction (Project 16-1 – Evergreen Boulevard Area)

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Derick Sonnenberg at 612-791-4350. Jon Halter with Hakanson Anderson is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jon can be reached at 612-282-0725.

Please note that all work indicated is weather pending and Subject to Change.

Next week, the Contractor plans to begin boulevard restorations along Evergreen Boulevard from 90th Avenue to 85th Avenue for topsoil placement and seeding. Remaining concrete work is scheduled for October 19. Manhole and valve adjustments in advance of final paving will be complete by early next week.

Final asphalt paving is currently planned for the week of October 24. Signing and striping will follow the installation of the final lift of asphalt.

MSA Street Reconstruction (Project 16-2 – Mississippi Boulevard Area)

The Contractor for this project is Forest Lake Contracting, Inc. The Contractor's 24-hour emergency contact is Tim Matteson at 651-248-4708. Ron Sample is the City's full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874.

Please note that all work indicated is weather pending and Subject to Change.

During the week of October 17, the Contractor plans to place asphalt on the segment of Mississippi Boulevard between Crocus Street and Xavis Street. Boulevard restorations will continue throughout all areas of the project.

MSA Street Reconstruction (Project 16-3 – Mississippi Drive Area; Segments of Crooked Lake Boulevard/128th Avenue)

The Contractor for this project is C.S. McCrossan Construction, Inc. The Contractor's 24-hour emergency contact is Wayne Fluharty at 612-919-3018. Zach Pfieffer is the City's full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243.

This project is substantially complete. Ongoing punch list items along Crooked Lake Boulevard, 128th Avenue, Round Lake Boulevard and Mississippi Drive will continue throughout next week. 

MSA Street Reconstruction (Project 16-4 – Segments of Xeon Street, 113th Avenue/Dogwood Street/115th Avenue, and Egret Boulevard)

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contact is Stewart Packer at 763-286-7341. Jason Huebscher is the City's full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704.

This project is substantially complete. Remaining seeding application and punch list items will continue along Egret Boulevard and other areas of the project the week of October 17. 