Street Reconstruction Update

85th Avenue Trail Construction (Project 14-27)

The City has requested ancillary widening of the new trail as it approaches the railroad tracks to reduce the sharp trail curvature, and to create additional buffer space where the trail is located behind the curb & gutter. This work is anticipated to occur this fall. 

MSA Street Reconstruction (Project 16-1 – Evergreen Boulevard Area)

The Contractor for this project is Park Construction Company. The Contractor's 24-hour emergency contact is Derick Sonnenberg at 612-791-4350. Jon Halter with Hakanson Anderson is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jon can be reached at 612-282-0725.

Please note that all work indicated is weather pending and Subject to Change.

Next week, the Contractor plans to complete roadway grading in advance of paving from 90th Avenue to just north of 85th Avenue. Asphalt paving is planned to occur in this area next week as well. However, a portion of Evergreen Boulevard just north of 85th Avenue will not be paved due to the oversaturated roadway base – additional time is required for this area to dry out. As soon as this occurs, curb & gutter will be installed, and the area will be paved.

Ancillary concrete and sidewalk work throughout remaining portions of Evergreen Boulevard is scheduled toward the end of next week.

MSA Street Reconstruction (Project 16-2 – Mississippi Boulevard Area)

The Contractor for this project is Forest Lake Contracting, Inc. The Contractor's 24-hour emergency contact is Tim Matteson at 651-248-4708. Ron Sample is the City's full-time project inspector. For specific questions or concerns this week, please contact Mark Hansen at 763-767-6465.

Please note that all work indicated is weather pending and Subject to Change.

During the week of October 3, the Contractor plans to pave Mississippi Boulevard from Direct River Drive to the first Crocus Street intersection. Asphalt driveway restorations are planned to occur from 108th Lane to Direct River Drive. Boulevard restorations will continue throughout all areas of the project.

 MSA Street Reconstruction (Project 16-3 – Mississippi Drive Area; Segments of Crooked Lake Boulevard/128th Avenue)

The Contractor for this project is C.S. McCrossan Construction, Inc. The Contractor's 24-hour emergency contact is Wayne Fluharty at 612-919-3018. Zach Pfieffer is the City's full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Zach can be reached at 612-710-8243.

Please note that all work indicated is weather pending and Subject to Change.

Irrigation repairs will occur in the drain tile replacement area along Mississippi Drive next week. Mailboxes are scheduled to be reinstalled on Mississippi Drive on Monday, October 3.

Boulevard restorations will continue throughout all of next week, and seeding will most likely occur the week of October 10. Final wear course paving is planned for Mississippi Drive on Wednesday, October 5.

MSA Street Reconstruction (Project 16-4 – Segments of Xeon Street, 113th Avenue/Dogwood Street/115th Avenue, and Egret Boulevard)

The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contact is Stewart Packer at 763-286-7341. Jason Huebscher is the City's full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 612-709-2704.

Please note that all work indicated is weather pending and Subject to Change.

Topsoil replacement is planned for Monday and Tuesday, October 3 and 4. Seeding is anticipated to occur late next week. Final asphalt wear course paving is planned for Wednesday and/or Thursday next week. 

Miscellaneous Trail Construction, Rehabilitation and Erlandson Park Pedestrian Bridge Replacement (Project 16-8)

This project is substantially complete. It included the replacement of a pedestrian bridge in Erlandson Park, as well as trail rehabilitation between Riverview and Dahlia Parks and construction of a new trail segment within Peppermint Stick Park. 