2016 Park Redevelopment Projects (Project 15-20)
Woodcrest – Work at Woodcrest is substantially complete, with the exception of the restroom structure which is anticipated to be installed in September. Minor turf restoration still remains on site and will be completed over the next few weeks as temperatures become more favorable. Work on the disc golf course will begin to ramp up now that the wetland delineation work is complete and approved; it is anticipated to be completed this fall.
Mason – Work at Mason is substantially complete, with the exception of the playground structure which has been scheduled for installation at the beginning of August. Minor turf restoration still remains on site and will be completed over the next few weeks as temperatures become more favorable.
Delta – All concrete work is now complete on the project, and trail paving was completed this week. Trees have been planted, and additional landscaping work will continue over the next couple of weeks. Site grading and trail backfilling will take place next week and turf restoration will be completed over the next few weeks as temperatures become more favorable. The picnic shelter is now complete, and the playground structure will be installed in early August.
Pheasant Ridge – Work at Pheasant Ridge is substantially complete. Minor turf restoration still remains on site and will be completed over the next few weeks as temperatures become more favorable. The acrylic coating for the basketball court will be applied next week, and the playground structure will be installed in early August.