2016 Park Redevelopment Projects (Project 15-20)
Woodcrest – All concrete work, trail paving and park landscaping is now complete. AgLime work is complete on the ball field and benches have been installed. The picnic shelter and benches were also installed. Foundations for the basketball hoops were set, and an acrylic coating will be applied next week. Fencing should be completed next week, and it is anticipated that the restroom structure will be installed in September.
Mason – All concrete work, trail paving and final grading is complete. The picnic shelter and basketball hoops are now installed, and the playground structure has been scheduled for installation at the beginning of August.
Delta – Concrete installation is now complete throughout the park. Work on the picnic shelter commenced and will continue into next week. Bituminous trail paving is planned to occur the week of July 11, followed by final grading. Once grading is complete, seeding and landscaping will occur.
Pheasant Ridge – All concrete work, bituminous trail paving and final grading is complete. The picnic shelter is complete, and benches were installed. Next week, crews will work on miscellaneous seeding and landscaping throughout the park. The playground structure will be installed in early August.