2016 Park Redevelopment Projects (Project 15-20)
Woodcrest – All concrete work and trail paving is now complete. The remainder of the AgLime will be installed on the ball field next week, with fencing and benches to follow. Picnic shelter erection continues and should be completed next week, with picnic table installation to follow. Seeding for the native planting areas occurred this week, along with tree planting. Minor turf restoration remains, and it is anticipated that the restroom structure will be installed in September.
Mason – All concrete work and trail paving is now complete. Minor grading activities and turf restoration are anticipated to occur next week. Picnic shelter erection continues and should be completed next week, with picnic table installation to follow. Seeding for the native planting areas occurred this week, and turf restoration in various areas should occur next week. The playground structure has been scheduled for installation at the beginning of August.
Delta – Site removals are complete on the project, and grading for the new facilities is substantially complete. Concrete curb installation is complete around the basketball court and playground area, with flatwork (sidewalk) areas to be installed next week. Trail base and paving will occur over the next two weeks.
Pheasant Ridge – All concrete work on the project is now complete. Seeding for the native planting areas occurred this week, and turf restoration in various areas will occur over the next two weeks. Work on the handicap parking area along Pheasant Ridge Drive is also complete. Picnic shelter erection continues and should be completed next week, with picnic table installation to follow. The playground structure will be installed in early August.