Northdale Boulevard/Redwood Street Signalization (Project 15-15)
The Contractor for this project is Valley Paving, Inc. The Contractor's 24-hour emergency contact is Dan Lorentz at 612-282-2070. Andrew Gunnick is the City's full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Andrew can be reached at 612-219-1878.
This week, hydrants on the north side of Northdale Boulevard were replaced. Curb and apron removal on the north side of the project occurred, followed by widening, grading and placement of aggregate base. Curb and gutter replacement is planned for Monday, June 20. Later in the week, crews plan to install sidewalk and driveway aprons, and pave the remaining road surface by the end of the week. Pending weather and other conditions, the majority of the work should be complete by the end of June.