2016 Park Redevelopment Projects (Project 15-20)
Woodcrest – All concrete work and trail paving is now complete. Trail backfilling is currently taking place and turf restoration, minor grading, and placement of agg. lime material in the ballfield to follow. The picnic shelter will be installed in approximately 1 week. Prep work for the native planting areas continues, with seeding to occur within 2 weeks. Testing of the restroom utilities and final pad work will occur next week. It is anticipated that the structure will be installed in late summer/early fall.
Mason – All concrete work and trail paving is now complete on the project. Trail backfilling is currently taking place, with turf restoration and minor grading work to follow. The picnic shelter will be installed in approximately 2 weeks. Prep work for the native planting areas continues, with seeding to occur within 2 weeks. The playground structure will be installed upon completion of all site improvements.
Delta – Site removals and layout of new facilities continues. Site tilling and grading activities have commenced and will continue next week. Concrete installation will occur around the playground structure and basketball courts in the next 1 - 2 weeks.
Pheasant Ridge – A majority of the concrete work is complete, with the remainder to be completed next week. Prep work for the native planting areas continues, with seeding to occur within 2 weeks. Work on the handicap parking area along Pheasant Ridge Drive should also begin next week and last approximately 2 weeks. The picnic shelter and playground structure will be installed upon completion of a majority of the site improvements.