MSA Street Reconstruction (Project 16-4 – Segments of Xeon Street, 113th Avenue/Dogwood Street/115th Avenue, and Egret Boulevard)
The Contractor for this project is North Valley, Inc. The Contractor's 24-hour emergency contact is Stewart Packer at 763-286-7341. Jason Huebscher is the City's full-time project inspector, and can be contacted anytime to respond to specific questions or concerns. Jason can be reached at 612-709-2704 (cell).
Construction is planned to begin the week of May 16. Initial work includes traffic control set up, removals, and the installation of temporary watermain on Xeon Street. Work is planned to focus on Xeon Street from May 16 to mid-June. The Contractor will work to keep Xeon Street open to traffic to the extent possible, but road closures will likely become necessary as the project progresses. Access to area businesses will be maintained at all times during construction. However, access may need to take place from either Creek Meadow Drive/114th Avenue or Northdale Boulevard depending upon the location of work on Xeon Street. Email updates regarding road closures will be provided to businesses on Xeon Street.
Work on 113th Avenue, Dogwood Street, and 115th Avenue is scheduled to take place between mid-June and mid-August. Work on Egret Boulevard is scheduled to take place from mid-July to the end of September.
Residents and businesses adjacent to the project and affected by construction were sent project information via US Mail this week.