2022 Street Reconstruction Project 22-1
4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard
The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
In the phase 3 area (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets) sod installations will be completed next week. Mailbox reinstallations will continue most of next week in phase 3. Temporary mail will remain in effect for the phase 3 area until all mailboxes have been reinstalled back to their permanent locations. Work on the new street sign replacements in the phase 3 area is expected to begin next week.
Work in the phase 4 area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street) is mostly complete. New street signs are expected in the phase 4 area next week. Remaining work includes paving the final lift of asphalt wear course pavement, and restorations at Vineyard Park.
Work in the phase 5 area (streets south of 119th Avenue between Kerry and Jonquil Street plus the Marigold and Kerry Street cul-de-sacs north of 119th Avenue and 117th Lane east of Northdale Blvd) next week includes placement of the asphalt base layer on Wednesday, September 14. Asphalt driveway restorations will be done as soon as the street asphalt has been placed. Boulevard restorations will also begin next week in phase 5.