2022 Street Reconstruction Project 22-1
4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard
The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
In the phase 3 area (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets) work will continue on boulevard repairs. Mailboxes will be reinstated next week in phase 3. This work is expected to continue into the following week. Temporary mail will remain in effect for the phase 3 area until all mailboxes have been reinstalled back to their permanent locations.
Work in the phase 4 area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street) is mostly complete. Remaining work includes paving the final lift of asphalt wear course pavement, and restorations at Vineyard Park.
The boulevard areas along the new sidewalk installed on 119th Avenue will be backfilled and restored next week.
Work in the phase 5 area (streets south of 119th Avenue between Kerry and Jonquil Street plus the Marigold and Kerry Street cul-de-sacs north of 119th Avenue and 117th Lane east of Northdale Blvd) includes removal of excess gravel material and tolerancing in advance of asphalt base paving. Asphalt base pavement for phase 5 is planned for September 14.