2022 Street Reconstruction Project 22-1
4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard
The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
In the phase 3 area (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets), work will continue with irrigation and boulevard repairs next week. Remaining concrete work has been rescheduled to be complete by early next week. Asphalt base paving is scheduled to be completed on remaining segments in phase 3 on Monday, August 15.
Work in the phase 4 area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street) includes irrigation, boulevard and sod restorations.
Fire hydrant, gate valve, and storm sewer catch basin replacements will continue throughout most of next week in the phase 5 area (streets south of 119th Avenue between Kerry and Jonquil Street plus the Marigold and Kerry Street cul-de-sacs north of 119th Avenue plus 117th Lane east of Northdale Blvd). Remaining concrete removals will also take place in this phase next week.
The schedule for pouring concrete for the new sidewalk on the north side of 119th Avenue is currently on hold.