2022 Street Reconstruction Project 22-1
4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard
The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
In the phase 3 area (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets), remaining hand poured curb and driveway aprons will be complete by Tuesday, August 9. Irrigation repairs will begin in phase 3 by late next week. Asphalt base course pavement is expected to be placed on phase 3 streets that are ready for asphalt between Monday and Tuesday next week. Asphalt driveway restorations are also planned for next week in phase 3.
Work in the phase 4 area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street) includes irrigation, boulevard and sod restorations. Asphalt base course pavement will also be placed on the remaining streets within phase 4 that don’t already have it.
Fire hydrant, gate valves, and storm sewer catch basin replacements will continue all next week in the phase 5 area (streets south of 119th Avenue between Kerry and Jonquil Street plus the Marigold and Kerry Street cul-de-sacs north of 119th Avenue plus 117th Lane east of Northdale Blvd).
Concrete for the new sidewalk on the north side of 119th Avenue is expected to be poured next week.