2022 Street Reconstruction Project 22-1
4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard
The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Miscellaneous valve, hydrant, and storm sewer replacements are planned to wrap up in the phase 3 area (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets) the week of July 18. Curb removals in the phase 3 area are now scheduled to take place next week on the north streets of phase 3.
In the combined project phase 4 area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street), asphalt base paving has been rescheduled to take place on the north streets of phase 4 by the middle of next week. Remaining curbs in phase 4 will also be installed on Vintage and Undercliff Streets, plus streets in the north portion of phase 4.
Miscellaneous valve, hydrant, and storm sewer replacements will begin within phase 5 (streets south of 119th Avenue between Kerry and Jonquil Street plus the Marigold and Kerry Street cul-de-sacs north of 119th Avenue plus 117th Lane east of Northdale Blvd) next week.