2022 Street Reconstruction Project 22-1
4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard
The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work is expected to begin in the first phase area of this project (Phase 3 - Wedgewood Drive between Round Lake Boulevard and 119th Avenue including adjacent side streets) next week, including continued saw-cutting of existing curb and driveways planned for eventual replacement.
Due to existing utility conflicts (Comcast) within the overall phase 3 area of the combined 22-1 and 22-2 projects (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets), the Contractor intends to begin work in the overall combined project phase 4 area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street) at the beginning of June. This is a change from the original schedule that was mailed to property owners at the beginning of May, which showed phase 4 starting in mid-July. An updated schedule will be mailed to affected properties as well.
Construction will continue in phase 3 per the original mailed schedule; however, the work will be limited primarily to utility and storm sewer pipe replacements. This schedule adjustment will allow Comcast additional time needed in the phase 3 area to relocate its facilities in advance of the street work.