2021 Street Reconstruction Project 21-2 – 3.6 miles of local streets (streets north of Coon Rapids Boulevard between Flamingo and Jay Streets north to 106th Avenue, Eagle Street to Avocet Street south of Egret Boulevard, and the neighborhood off Foley Boulevard between 95th and 97th Lanes)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Area 1 (streets including Hummingbird Street, Grouse Street, Flamingo Street, 104th Avenue, Ibis Street, Jay Street, and 106th Avenue) is now substantially complete. Completion of new sign installations are expected early next week.
Next week in Area 2 (streets east of Egret Blvd known as Egret Estates), work includes continued boulevard restorations. Topsoil and sod installations may begin by the end of next week.
Work in Area 3 (streets east of Foley Boulevard and north of TH 610 up to 97th Lane) next week includes completion of topsoil and sod placements.
The final lift of asphalt pavement in Areas 2 and 3 is anticipated during the week of October 4.
Property owners should contact the Contractor and/or project inspector this fall if they have any ongoing issues with their irrigation system.