2021 Street Reconstruction Project 21-2 – 3.6 miles of local streets (streets north of Coon Rapids Boulevard between Flamingo and Jay Streets north to 106th Avenue, Eagle Street to Avocet Street south of Egret Boulevard, and the neighborhood off Foley Boulevard between 95th and 97th Lanes)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Area 1 (streets including Hummingbird Street, Grouse Street, Flamingo Street, 104th Avenue, Ibis Street, Jay Street, and 106th Avenue) is now substantially complete. Final sign installations in this area will take place within the next couple of weeks.
Next week in Area 2 (streets east of Egret Blvd known as Egret Estates), work will include asphalt driveway restorations and tolerancing of the gravel base on each street.
Work in Area 3 (streets east of Foley Boulevard and north of TH 610 up to 97th Lane) next week includes boulevard restorations, topsoil placement and irrigation repairs. Mailboxes are expected to be reinstalled on September 13 and 14.
ATTENTION RESIDENTS PLANNING ON FULL DRIVEWAY REPLACEMENTS: If a portion of your driveway apron has been removed as part of the City’s construction project and you are planning to have your own contractor install a full new driveway, please email Jason Huebscher at jhuebscher@coonrapidsmn.gov with details (property address, timing of installation, etc.). The City will work with you to issue a credit for the work that would have been completed under our project and will direct the City’s Contractor to exclude your driveway apron from its restoration plans.